LEC successfully executed mold remediation and interior demolition at Randolph Air Force Base, ensuring minimal disruption to occupants while coordinating with multiple trades.
Project Scope:
Interior Demolition – Removal of 65,000 sq. ft. of drywall ceilings, walls, VCT tile, ceramic tile, carpeting, and system furniture
Critical Systems Demolition – Safe removal and replacement of cabinetry and other structural components
Advanced Containment Measures –
Critical poly-sheet barriers (4-6 mil) to isolate work zones
Negative air machines for mold containment and ventilation
Safety & Compliance –
Demarcated work areas with barricade tape and warning signs
Strict adherence to OSHA standards & Texas State Protocols
Approved work and safety plans
We completed the project on schedule in under 90 days, ensuring a safe, compliant, and efficient restoration while maintaining air quality and occupant safety.