Regions Center Headquarters Building 30 Story Tower

LEC completed a complex asbestos abatement and selective demolition project at the Regions Headquarters Building in downtown Birmingham, AL, ensuring minimal disruption to bank operations.

Project Scope:

Asbestos Removal & Disposal – Ceiling tile, drywall, and structural steel fireproofing

Occupied Building Work – Maintaining active access for bank customers and employees

Specialized Scaffold Erection – Elevated work platform 25+ feet above floor level

Selective Demolition – Removal of ceiling tile grid and light fixtures

Safety & Compliance – Approved work and safety plans

Project Execution:

Conducted work at night and on weekends to minimize impact

Managed logistical and physical challenges within an active commercial environment

Completed the project on schedule and without incident

Contract Value: $244,700 across two purchase orders (PJ153110 & PJ153241)

Performance Period: August 19 – November 26, 2016

We delivered safe, efficient, and seamless remediation for this high-profile client, demonstrating expertise in sensitive environmental services.